Sunday, 26 July 2020

Technical terms for civil engineers

● maximum diameter of bar in slab should      not exceed = (1/8)×thickness of slab 

● dimensional tolerance of cube size = 2mm

● standard slope for staircase = 25° to 40°

● volume of one cement
                                      bag = 0.03472 m                                                               cube or 1.22 cft

● 1 inch = 8 soot

● 


Thursday, 11 June 2020

How to calculate the cost of one column



Example:


   Column size = 250mm×250mm

   Column height = 3.1 m

   Steel bar used = 4 nos

   Dia of bar        = 12mm 

Stirrup spacing = 150mm

Dia of stirrup     = 8mm

Volume of column = length×breadth×height
                                   = 0.25×0.25×3.1 m cube 
                                   = 0.19375 m cube 

Concrete grade M20 mix ratio-1:1.5:3

1 m cube concrete 
                required - 8 bag cement 
                                 - 15 cft sand
                                 - 30 cft aggregate 

                        Cement = 0.19375×8
                                        = 1.55 bag
   Rate Rs-380 per bag = 1.55×380
                                        = Rs-589

                         Sand     = 0.19375×15 cft
                                        = 2.9 cft
       Rate Rs-45 per cft = 2.9×45 
                                        = Rs-131 

                   Aggregate = 0.19375×30 cft
                                        = 5.81 cft
       Rate Rs-30 per cft = 5.81×30 
                                        = Rs-175

  Steel bar
    (i)  Main bar = 4×3.1 m
                            = 12.4 m
            Weight   = (D×D× length)/162  kg
                            = (12×12×12.4)/162  kg
                            = 11.02 kg
 
       (ii) stirrup  bar             
 No. of stirrup  = (height/spacing )+1
                            = (3.1/0.150)+1
                            = 21.66 
                 Let     = 22 nos

Total stirrup length = 22×0.648 m
                                     = 14.25 m
                  Weight      = (D×D×length)/162 kg
                                     = (8×8×14.25)/162 kg
                                     = 5.62 kg
  Total steel weight   = 11.02+5.62 kg
                                     = 16.64 kg
                              Let = 17 kg

    Rate Rs-50 per kg = 17×50 
                                    = Rs-850

Total column cost = 589+131+175+850
                                   = Rs-1745 ans.

  

Wednesday, 3 June 2020

1000 sqft slab casting cost 2020

        
  
  Slab size = 25×40 sqft 
                              = 1000 sqft 

 Slab thickness = 150 mm
   
         Beam size = 225mm×300mm

Volume of slab = 1000×0.5  cft
                              = 500 cft
                           
Horizontal beam
              volume = (length×breadth
                                 ×depth×no of beam)
                             = (25×0.75×(1-0.5)×4)
                             = 37.5 cft
Vertical beam
            volume  = (40-(4×0.75)×0.75×
                                (1-0.5)×3)
                            = 41.625 cft

Total slab volume = 500+37.5+41.625 cft
                                    = 579.12 cft

         Cft to m cube = 579.12÷35.315
                                    = 16.40 m cube 

Ready mix concrete
                         (RMC) = Rs-4500/m cube 
Total concrete cost = 16.40×4500
                                      = Rs-73800

Labour cost               = Rs-750/m cube 
                                      = 16.4×750 
                                      = Rs-12300


Total slab casting
                             cost = 73800+12300
                                      = Rs-86100



Note: for more information about the civil engineering watch video link below. 
https://youtu.be/ftzMHZcTpN8
                                           

Tuesday, 2 June 2020

House construction cost of 2000 sqft and materials quantity

  
   Class-A building cost
    Rs-1600 to Rs-2500 per sqft 

  Class-B building cost
   Rs-1000 to Rs-1200 per sqft 

  Class-C building cost
  Rs-750 to Rs-900 per sqft 


Materials quantity 

     1. Cement = 800 bags
     2. Sand      = 3000 cft
     3. Aggregate = 2000 to 2500 cft
     4. Steel bar   = 7 to 8 ton
     5. Bricks        = 18000 to 20000 


S.no    Items              %              cost

1.        Labour             25%          Rs-600000
2.        Bricks               12%          Rs-288000
3.        Cement             13%          Rs-312000
4.        Steel bar           10%          Rs-240000
5.        Sand and 
           Aggregate         7%            Rs-168000
6.        Doors and
           Windows          12%          Rs-288000
7.        Electric work   8%            Rs-192000
8.        Water and 
           Sewage              10%          Rs-240000
9.        Extra                  3%            Rs-72000

Grade of concrete and mix ratio


Monday, 1 June 2020

How to calculate load carrying capacity of the column




Example:

    Load = 400 kN

    Column size = 300mm×300mm

  No of steel bar used in column 4 nos

Diameter of bar used in column = 16mm

M20 grade concrete used 

Grade of steel = Fe 415 


  Formula:
     
     Pu = (0.4fck.Ac)+(0.67fy Asc)

   ( From IS-456 2000 code page no 71)

Where .

     Pu = axial load on the member
     Ac = area of concrete 
    fck = characteristic compressive 
              strength of the concrete 
      fy = characteristic strength of the
              compression reinforcement 
   Asc = area of longitudinal reinforceme
              -nt for column
      fck = 20
        fy = 415 


    Ac = Ag-Asc
    Ag = gross area of column 


    Ag = 300×300 mm square 
          = 90000 mm square 


   Asc = 4×((3.14×16×16)÷4) mm square 
           = 804.24 mm square 


    Ac = (90000-804.24) mm square 
          = 89196 mm square 


   Pu = (0.4×20×89196)+(0.67×415×804)
         = 937120.1 N
         = 937.1 kN ans.

According to the IS-456 2000 
Safety of factor = load /1.5
                               = 624.74 kN



Note: for more information watch video link below. 

https://youtu.be/pFDmAt0EWvE

    

Friday, 29 May 2020

How to calculate slab self weight


Example:

    Slab size = 3m×5m
                     = 15 m square 

  Slab Thickness = 0.15m or 15cm or 150mm

 Concrete density = 2400 kg/meter cube 

 Steel density         = 7850 kg/meter cube 


 Volume of slab = 0.15×1×1 m square 
                             = 0.15 m cube   
                             = 0.15×2400 kg/m square 
                             = 360 kg/m  square 

 0.8% steel provided to
 the total slab volume = (0.8/100)×0.15×7850
                                         = 9.42 kg/m square 


 Slab self weight = 360+9.42 kg/m square 
                               = 369.42 kg/m square 
                               = 3.69 kN/m square 
        Live load      = 2kN/m square 
        Dead load    = 1 kN/m square 


Slab self weight = 3.69+2+1 kN/m square 
                              = 6.69 kN/m square 


Total slab self weight = 6.69×15 kN
                                          = 100.35 kN ans.


According to IS-456 2000 
 Safety of factor = 1.5×load 
                     SOF  = 1.5×100.35 kN
                              = 150.52 kN