1000 sqft slab casting cost 2020

        
  
  Slab size = 25×40 sqft 
                              = 1000 sqft 

 Slab thickness = 150 mm
   
         Beam size = 225mm×300mm

Volume of slab = 1000×0.5  cft
                              = 500 cft
                           
Horizontal beam
              volume = (length×breadth
                                 ×depth×no of beam)
                             = (25×0.75×(1-0.5)×4)
                             = 37.5 cft
Vertical beam
            volume  = (40-(4×0.75)×0.75×
                                (1-0.5)×3)
                            = 41.625 cft

Total slab volume = 500+37.5+41.625 cft
                                    = 579.12 cft

         Cft to m cube = 579.12÷35.315
                                    = 16.40 m cube 

Ready mix concrete
                         (RMC) = Rs-4500/m cube 
Total concrete cost = 16.40×4500
                                      = Rs-73800

Labour cost               = Rs-750/m cube 
                                      = 16.4×750 
                                      = Rs-12300


Total slab casting
                             cost = 73800+12300
                                      = Rs-86100