Example:
   Column size = 250mm×250mm
   Column height = 3.1 m
   Steel bar used = 4 nos
   Dia of bar        = 12mm 
Stirrup spacing = 150mm
Dia of stirrup     = 8mm
Volume of column = length×breadth×height
                                   = 0.25×0.25×3.1 m cube 
                                   = 0.19375 m cube 
Concrete grade M20 mix ratio-1:1.5:3
1 m cube concrete 
                required - 8 bag cement 
                                 - 15 cft sand
                                 - 30 cft aggregate 
                        Cement = 0.19375×8
                                        = 1.55 bag
   Rate Rs-380 per bag = 1.55×380
                                        = Rs-589
                         Sand     = 0.19375×15 cft
                                        = 2.9 cft
       Rate Rs-45 per cft = 2.9×45 
                                        = Rs-131 
                   Aggregate = 0.19375×30 cft
                                        = 5.81 cft
       Rate Rs-30 per cft = 5.81×30 
                                        = Rs-175
  Steel bar
    (i)  Main bar = 4×3.1 m
                            = 12.4 m
            Weight   = (D×D× length)/162  kg
                            = (12×12×12.4)/162  kg
                            = 11.02 kg
       (ii) stirrup  bar             
 No. of stirrup  = (height/spacing )+1
                            = (3.1/0.150)+1
                            = 21.66 
                 Let     = 22 nos
Total stirrup length = 22×0.648 m
                                     = 14.25 m
                  Weight      = (D×D×length)/162 kg
                                     = (8×8×14.25)/162 kg
                                     = 5.62 kg
  Total steel weight   = 11.02+5.62 kg
                                     = 16.64 kg
                              Let = 17 kg
    Rate Rs-50 per kg = 17×50 
                                    = Rs-850
Total column cost = 589+131+175+850
                                   = Rs-1745 ans.