Wednesday, 29 April 2020

RCC column reinforcement details

Estimation of column reinforcement details. With example
Example:
   

                  



More information about the RCC column reinforcement details please watch video link below. 
https://youtu.be/OsvZGt5TZtk

Tuesday, 28 April 2020

RCC column footing reinforcement details



Example:
             
                      



For more information about the example or full details about footing reinforcement details watch video link below. 
https://youtu.be/hCre-Ma20dE


Monday, 27 April 2020

How to check soil bearing capacity in construction site

Procedure: 

       (i) excavate a pit of required depth.

      (ii) take a iron cube or ball (whose                        dimension and weight are known)

     (iii) drop the cube or ball several times,                from known height on the excavate                pit.

     (iv) calculate the average value of the                    depth.


        R = (w×h)/d

Where
           R - ultimate resistance of soil in kg.

           d - average depth of impression in                         (cm).

          w - weight of solid ball or square cube                   in kg.
     
           h - height of fall ball of cube.


Example:
           Cube weight = 5 kg

          Height of fall = 150 mm

          Depth of impression - 9 cm,8.5 cm,6                                              cm,5 cm and 4 cm


Solution:- 

                  Average depth of impression
         d   = (9+8.5+6+5+4)/5 cm
              = 6.5 cm

         R  = (w×h)/d
              = (5×150)/6.5
              = 115.38 kg

Then, resistance of soil per unite area

               = R/A   kg/cm×cm

               = 115.38/(15×15)   kg/cm×cm
               = 0.51 kg/cm×cm


Safe bearing capacity of soil = R/(A×fos)

fos - resistance of soil per unite area reduce           2 to 3 times

 Safe bearing capacity of soil                                                    = 115.38/(15×15×2) kg/ cm×cm
                        = 0.256 kg/ cm×cm ans.
       

For  more  information  about this topic watch video link below.

https://youtu.be/sRspDdTRbVI

Facebook link.
https://www.facebook.com/sehbud.alam.52

Twitter link.
https://twitter.com/Sehbudalam7?s=09

Telegram link.
https://t.me/officialtkalam

Thnk you for visit.

Saturday, 25 April 2020

How to find size of footing

Procedure: requirement

          . Load on it

          . Bearing capacity of soil



Formula = (load + safety factor (10% of                           load))/( bearing capacity of                             soil)


Example: 
                Load = 1500 kN

        Bearing capacity of soil = 200kN/m                                                                square 


Solution: 
                  Given
            Load = 1500 kN

Bearing capacity of soil = 300 kN/m square

      Safety factor = 10% of load
                              = (10/100)×1500
                              = 150 kN

Safe soil bearing = soil bearing                                    capacity       capacity/2
                               = 300/2 kN/ m square
                               = 150 kN / m square


Area of footing =( load + safety factor)/                                         safe soil bearing capacity
                            = (1500+150)/150 m×m
                            = 1650/150 m×m
                            = 11 m×m

Footing size square 
                     a×a = 11 m×m

                         a = 3.316 m ans.
             
                     

How to find size of column

According to IS-456 2000 find out the size of column need.

       . Load

       . Grade of concrete
   
       . Characteristic strength of the                           compression reinforcement

Formula:
                 Pu = (0.4fck×Ac)+(0.67×Fy×Asc)

   Where  Pu = ultimate load
                Fck = characteristic compressive                                strength of the concrete         
                  Ac = Area  of concrete
                  Fy = characteristic strength of the                             compression reinforcement
                 Asc = area of longitudinal                                             reinforcement for concrete 
             

Example: imposed load 2000 kn act on                the column size M20 grade Fe 415                grade steel. Find out the size of                    column.
                         
Solution: 
         
               Given 
                            Pu = 2000 kn
      
                           Fck = 20 N/mm square 

                           Fy   = 415 N/mm square 

Safety factor = 10% of load 
                        = (10/100)×2000 kn 
                        = 200 kn 
     Total load = 2000+200
                        = 2200 kn

   Grosss area= 100%
                Asc  = 1% Ag
                  Ac  = 99% Ag

                   Pu = (0.4×fck×Ac)+(0.67×fy×Asc)

 2200×1000    = (0.4×20×0.99Ag)+                                                  (0.67×415×0.01Ag)
           
  2200×1000   = 7.92Ag+2.7805Ag

  22000×1000 = 10.7005Ag

                   Ag = (2200×1000)/10.7005

                   Ag = 205597.869 mm square

Square size of column

                a×a = 205597.869 mm square
             
                    a = 453.42 mm ans.                     
                     


More information about size of column watch video link below. 
https://youtu.be/kQdKN8-vA_c

Friday, 24 April 2020

What is aggregate

What  is aggregate  
   Aggregate is a granular materials that act as skeleton and filling components in concrete and mortar, such as manufactured sand,natural sand,gravel,crushed stone and recycled concrete. Aggregate has a wide range of application in construction and other industries. 
                           



Types of aggregate 

    (i) coarse aggregate 

    (ii) fine aggregate 


What is coarse aggregate 
         Coarse aggregate will not pass through a sieve with 4.75 mm opening no 4 is portion of the concrete which is made up of the larger stones embedded in the mix concrete contains there ingredients, aggregate size larger than 4.75 mm is called coarse aggregate. 
               



What is fine aggregate 
         If the aggregate size is less than 4.75mm then it is called as fine aggregate. The minimum size of fine aggregate is 0.075mm is using for concreting work.
                   
  


Difference  between coarse aggregate and fine aggregate. 

Wednesday, 22 April 2020

How to find depth and breadth for beam

According to the IS-456 2000 code we can find depth and breadth of beam easy way need few requirement like length of beam according to length of beam we can find out depth and breadth of beam.


Depth of beam = length of beam/20

Example:
           A beam length 5m find out the depth and breadth of beam.
Solution:-
           Given
                       L= 5m

 Depth of beam = length of beam/20 m
                             = L/20 m
                             = 5/20 m
                             = 0.25 m
                             = 250 mm

Breadth of beam = depth of beam/1.5
                                = 250/1.5 mm
                                = 166.67 mm
                                = 170 mm

According to this example you can find out depth and breadth of beam easily. You can watch also below link
https://youtu.be/oZ2NnEr0M1Y