Requirement of cement, sand and aggregate for 1 cumec concrete volume ratio
According to is-456 2000 dry concrete volume is equal to 1.54 to 1.57 wet concrete volume.
For 1 cumec volume=(1m×1m×1m)
Dry volume = 1 meter cube
Wet volume = 1×1.54 meter cube
= 1.54 meter cube
Example: requirement of cement, sand and aggregate for 1 meter cube volume in M20 grade concrete mix ratio 1:1.5:3
Ans:
Volume of 1 meter cube =1.54 meter cube
Volume of cement= 1.54/5.5 meter cube
= 0.28 meter cube
In kg = 0.28×1440 kg
= 403.2 kg
Volume of sand = 0.28×1.5 meter cube
= 0.42 meter cube
In cft = 0.42× 35.315 cft
= 14.832 cft
Volume of aggregate
= 0.28×3 meter cube
= 0.84 meter cube
In cft = 0.84×35.315 cft
= 29.664 cft
Requirement of cement, sand and aggregate for for one cube (150mm×150mm× 150mm) concrete volume
According to the IS-456 2000 volume of dry concrete equal to 1.54 to 1.57 wet volume of concrete.
For one cube (150mm×150mm×150mm)
Dry volume = 0.003375 meter cube
Wet volume = 0.003375×1.54 meter cube
= 0.005197 meter cube
Q. Requirement cement, sand and aggregate for one cube (150mm×150mm×150mm) in M20 grade mix ratio 1:1.5:3
Ans. Volume of cube = 0.003375 meter cube
Cement = 0.005197/5.5
= 0.0009449 meter cube
In kg = 0.0009449×1440 kg
= 1.36 kg
Sand = cement volume ×1.5 meter cube
= 0.0009449×1.5 meter cube
= 0.001417 meter cube
In cubic feet (cft)
Cft = 0.001417×35.315 cft
= 0.05 cft
Aggregate in cft
= volume of cement ×3 meter cube
= 0.0009449×3 meter cube
= 0.002834 meter cube,
Cft = 0.002834×35.315 cft
= 0.1 cft
Note: meter cube = cubic meter, cft( cubic feet), 1 cubic meter = 35.315 cubic feet.
According to is-456 2000 dry concrete volume is equal to 1.54 to 1.57 wet concrete volume.
For 1 cumec volume=(1m×1m×1m)
Dry volume = 1 meter cube
Wet volume = 1×1.54 meter cube
= 1.54 meter cube
Example: requirement of cement, sand and aggregate for 1 meter cube volume in M20 grade concrete mix ratio 1:1.5:3
Ans:
Volume of 1 meter cube =1.54 meter cube
Volume of cement= 1.54/5.5 meter cube
= 0.28 meter cube
In kg = 0.28×1440 kg
= 403.2 kg
Volume of sand = 0.28×1.5 meter cube
= 0.42 meter cube
In cft = 0.42× 35.315 cft
= 14.832 cft
Volume of aggregate
= 0.28×3 meter cube
= 0.84 meter cube
In cft = 0.84×35.315 cft
= 29.664 cft
Requirement of cement, sand and aggregate for for one cube (150mm×150mm× 150mm) concrete volume
According to the IS-456 2000 volume of dry concrete equal to 1.54 to 1.57 wet volume of concrete.
For one cube (150mm×150mm×150mm)
Dry volume = 0.003375 meter cube
Wet volume = 0.003375×1.54 meter cube
= 0.005197 meter cube
Q. Requirement cement, sand and aggregate for one cube (150mm×150mm×150mm) in M20 grade mix ratio 1:1.5:3
Ans. Volume of cube = 0.003375 meter cube
Cement = 0.005197/5.5
= 0.0009449 meter cube
In kg = 0.0009449×1440 kg
= 1.36 kg
Sand = cement volume ×1.5 meter cube
= 0.0009449×1.5 meter cube
= 0.001417 meter cube
In cubic feet (cft)
Cft = 0.001417×35.315 cft
= 0.05 cft
Aggregate in cft
= volume of cement ×3 meter cube
= 0.0009449×3 meter cube
= 0.002834 meter cube,
Cft = 0.002834×35.315 cft
= 0.1 cft
Note: meter cube = cubic meter, cft( cubic feet), 1 cubic meter = 35.315 cubic feet.